2,000 cubic metres of concrete
| Location | Pluto LNG Project, Burrup Pennisula WA |
| Principal | Woodside |
| Killarnée's client | Decmil Australia |
| Construction period | May - September 2011 |
| Scope of works |
Upgrade the Field Auxiliary Room No. 2 (FAR 2) from 'Cyclone Rated' to 'Blast Proof Rated'. This is to be achieved by constructing a concrete external shell around the existing building. The walls of the new sheel will be 400mm thick reinforced concrete to support a new 200mm thick reinforced concrete roof. |
| Construction activities |